Will Expect More
30.01.2008 Radikal
ANKARA - In order to install 78 thousand megawatt wind power plants in Turkey, applications made in November 1, 2007 were no transaction. While investors to process interest for a total of 780 million USD collateral letter, there was to remove the law in order to make withdrawals between wind power plants applying multiple applications to the same place.
[[T]] In order to install wind power plant on November 1, 2007, 751 applications for the power of the total 78 thousand megawatts (MW) were made. For each MW application from investors, there was a letter of L$ 10 thousand. In this way, the amount of the collected collateral found 780 million USD. Investors will pay interest in about million USD in three-month periods for collateral letter that they use from Banks. First interest will take place at the end of this month. [[[T]] [[T][6] ] ]]]]]]EPDK Sprinkler examinations of wind power plant applications. The only application is expected to be born in a short time of assessment for plants in Bolu, Zonguldak, Adıyaman, Malatya, Kilis, Niğde and Kütahya. However, 751 is about 700 applications for the same province for 6 and above. For example, 113 in Izmir, 93 in Çanakkale, 86 in Balıkesir, 63 in Hatay, 47 applications in Istanbul. Applications for these cities consist of high-volume applications as megawatts.
]]
As referenced in multiple applications made for the same region or the same substation, e.g. e.g. in this regard, the EPDK does not have any transaction. When investors who apply for the plant continue application to process interest for collateral letters in Banks, they are going to be able to eject between multiple applications. However, it will not be enough to remove the law for it. A pharmacy will be healthy to determine the necessary procedures and principles.
by the Ministry of Energy, in order to make tenders for multiple applications for wind power with the threat of the law bill on supply safety in energy, Turkey Electrical Transmission Inc. authorized by '(TEİAŞ). According to this design, the tender will be held to determine the company that resembles the highest level of accession to the same substation center. After doing this tender, the results will be cent to EPDK. The challenges of companies to share are used only in transmission line investments by TEİAŞ.
Can last months [
]It is reported to be removed and the tender, and then find the months of the assessment process of the EPDK. During this time, investors will continue to pay interest for collateral letters. [
If the application has been applied to install the wind power plant up to 78 thousand MW, as well as due to the capacity of both applications, and transmission lines, it is necessary to note that all of the applications turn into investment.
]]Pay will be 20 percent
] [the officials of the wind power plants should be between 10-20 percent of the share in their total electrical production capacity, since electricity production is connected to weather conditions, they have taken into consideration that the capacity above 20 percent can not be met. [email protected] [
Activities are the state of absorption of production plants according to the demand of consumption of electricity, for example, when an natural gas or coal-powered thermal power plant reducing demand, they stressed that wind power plants can only produce electricity as long as wind. Thus, the enemy license that the wind power plant will enter every year should be determined by taking into account this situation, expressed that the wind power plant of 20 thousand MW in the middle run in Turkey could be activated. [
[Will be less
If the wind power plant license of approximately 2 thousand 500 MW is into account byEPDK, the applications will be promised to invest at the maximum of 17 thousand 500 MW section.
Rüzgar Energy and Water Power Plants Association of Businessmen (RESSİAD) President Tolga Bilgin said that they are on the side to have an appointment criticization cc in applications, but as the review period extends, the investors stressed that the costs they paid for collateral letters.
[The Information that records of the Qualification should actually be determined before the application is accepted, but due to the fact that the application of the wind license for a long time, an intense print on the EPDK expressed that the work comes in a while because it was believed.. The information said that in the places where the applications are not conflicted, the EPDK’s review and assessment has started to be hopeful of being cockroaches with the speed of work. On the other hand, a group of businessmen called wind power plant investors were discovered that they would like to be accelerated by meeting with the Minister of Energy on Thursday, Hilmi Güler.
Source: News