Gama Energy’s two wind power plants announced TSKB provides 44 million euros credit

] [[T]]GAMA Holding Inc. and GAMA Energy Inc. with 50 percent partnerships of GE Energy Financial Services, a partnership of General Electric. The first wind energy investment in Turkey started. [[[T]] [[

GAMA Energy Inc., the projects in İzmir and Çanakkale will be in total 32.5 megawatt board power and will cost 54 million euros. For the project, from TSKB to 44 million euros, 2 years of unpaid 11-year-term credit will be used. [

GAMA Energy A.Ş speaking at the signature ceremony of 44 million euros creditor from TSKB for projects. General Manager M. Arif Özozan reserves that Gama has already been a 2,300 megawatt operational portfolio and aim to remove it in 4,000 megavata.

]

In the press release common from GAMA Energy and GE, Sares Wind Power Plant will consist of 9 valves and will have 22.5 megawatts installed power, the Montenegro wind power plant will consist of 4 axles and have 10 MW installed power. The Windshields in the power of 2.5 Copyright © 2018. All Rights Reserved.

Sares wind power plant’s construction work can start to produce energy at the end of the year starting next week. Montenegro wind power plant can work in the first quarter of 2011.

Thanks to these investments that will be made, the electricity needs of 59,000 homes in Turkey can feed from wind energy, and more than 80.000 tons of greenhouse gas emissions per year.